С»ÆѼÊÓƵ

Back
Insights
Employees sitting in G&T office
Putting Tenants First - Future Proofing Sustainable Spaces for Life Sciences
Back
G&T employee with Apprentice
Building future skills at Broadgate
Find out more
Back
Soldiers Adobe Stock 39369548
Why the built environment provides a great career path for military leavers
Discover more
IT engineer working with laptop in data centre full of active rack servers

Data Centre Power Intensification

Provision of new additional power and cooling infrastructure to deliver an additional 18MW of IT power to the facility.

A new structural tower was required to be built stretching the full height of the 10-storey building, which included tying back into the structure of the main building to house the additional plant facilitating the increased IT load.

The scope included enhancing the MV and LV systems including addition of 15 1.6MW DC generators as well as miscellaneous MEP works to fire protection, lifts and communications.

Client

Confidential

Location

London

Next Project

Data Centre Power Upgrade

View Project
Copy the URL below and share: