С»ÆѼÊÓƵ

Back
Insights
Employees sitting in G&T office
Putting Tenants First - Future Proofing Sustainable Spaces for Life Sciences
Back
G&T employee with Apprentice
Building future skills at Broadgate
Find out more
Back
Soldiers Adobe Stock 39369548
Why the built environment provides a great career path for military leavers
Discover more
Modern interior of server room in data centre

State Street Bank

G&T acted as cost managers and CDM co-ordinator for the expansion of a live data centre to provide an additional 350m² of net technical area.

Works included two 800kVA UPS modules, four PDUs and six CRAC units with associated works in a 10 week programme.

Next Project

JPMC Remote Data Centre

View Project
Copy the URL below and share: